Moody Point Fire and Drainage Retention Pond

 

The following summary of our status with the Newmarket Conservation Commission was prepared by Russ Simon for the Waterfront Association but we felt this should go out to the entire Association as well.  I want to emphasize that our opposition to the construction in wetlands is both a reflection of our desire to protect the environment at Moody Point generally, and their particular role in the mitigation of storm-water runoff we now experience.  Ultimately, most of the run-off from our community finds it way onto Lot#4.  Where and how it is handled is of critical importance to us in avoiding erosion,  unplanned swamps, and unfiltered feed to the Bay.

 

Regards,

Jim Fitzpatrick, President MPCA

 

 __________________

 

On 11/16/05 I received two registered letters officially notifying me, as President of the Waterfront Association, and you, as members of the Waterfront, that two applications had been submitted by New Hampshire Soils (representing the Moody Point Company - Walter Cheney) to the State's DES (Department of Environmental Services) requesting approval to build on the two lots in Osprey Circle (Lots 5-1-1 & 5-1-2) and the one lot next to the Fire Pond Road (Lot 2-7).  Two of these three lots have been classified by the State as Statutory Wetlands and one is adjacent to the Wetland.  We, the Waterfront, received these letters as we are abutters to all three of these properties.  Please see copies of the letters attached.  My email will constitute notification to you.  Letters were also delivered to the MPCA and other individuals, as abutters to one or more of these lots.

 

The State DES applications were submitted to the Town & the State on the morning of 11/17/05.  I made one copy of each application shortly after being delivered to Town Hall.  Each application is around 150 pages.

 

As best as I know the process today, the application to build on Wetlands must be approved by the State's DES and also the Town has to approve a local Conditional Use Permit before any construction would be allowed.  In addition, the application is to be reviewed by the Newmarket Conservation Commission for their opinion.  Though the Newmarket Conservation Commission has no official role in the application approval process, their opinion carries weight with the Town and the DES.

 

Jim Fitzpatrick, as President of the MPCA and I, as President of the Waterfront and Secretary of the MPCA, are beginning discussions with the State DES, the Town and the Conservation Commission notifying them of our opposition to any building on these lots due to the current and ongoing drainage problems at Moody Point and the lack of an existing approved drainage plan for the Moody Point Community.  This opposition is supported by the MPCA Board as well as a petition signed by at least 88 members of the MPCA.

 

To date Jim, I and another dozen or so people attended the recent Newmarket Conservation Commission Meeting on 11/17/05 where NH Soils was initially presenting the applications to the Commission for their approval and support.  During the presentation we briefly informed the Commission of our drainage problems at Moody Point and that we were working with both the Town and the UNH Storm Water Management Center on developing solutions to our problems.  We also informed the Commission that no record of the approved drainage plan for Moody Point exists - not with the State, the Town, the County, the Developer or the Engineering firm that did the original plan in the mid-1980's and as a result there was no drainage plan for Moody Point.  We also provided the Commission with a copy of the MPCA member's petition opposing building on the Wetlands lots.

 

The Commission decided that they needed time to study the recently delivered application, do a site walk of the lots in question at Moody Point and perhaps have an engineering review of the plans in the application.  As a result, they would ask the State for a 40 day extension to review the application in detail before issuing an opinion.  They also agreed to do a site inspection of the lots, currently planned for Saturday, 12/3/05 at 9 AM.  In addition, they said they were interested in getting educated as to our  drainage process with the Town and were most interested in what the UNH team had to say.

 

That's the status of the Wetland's Applications at the moment.  Jim and I will continue to follow-up with the State, Town & Commission on our Community's concerns and issues.

 

As an additional note, in my ongoing discussions with the Town Administrator and his staff on getting some work done on the roads and road beds where we have significant deterioration and standing water, I have been informed that the Newmarket Public Works Department should be out at Moody Point for a couple of days early next week to work on some of the problem areas.  Stay tuned.

 

Regards,

 

Russ